Summary Transportation Improvement Program - Carryforward Amounts
Program Period: Fiscal Years 2013 to 2018 - Starting 12/1/2012
Selected: All
6-Year
Total Cost
PIN
Route/From-To
Worktype/Cat
Project Description
B-00877
ITS-PASSAGE Network 2015
@ Various
Signals
Preservation
PASSAGE Field Support
ITS-PASSAGE Network 2016
@ Various
Signals
Preservation
ITS-PASSAGE Network 2017
@ Various
Signals
Preservation
B-01148
ITS-PASSAGE Network 2018
@ Various
Signals
Preservation
B-01104
ITS-Rollins-BlueToad
Grand Ave to IL Rte 132
Signals
Modernization
B-01038
ITS-Sheriffs Dept CAD
@ Various
Signals
Modernization
Project Totals
B-00511
ITS-Waukegan-Grand Ave
IL Rte 131 to Sheridan Rd
Signals
Modernization
Upgrade Traffic Signal Interconnect
Project Totals
B-00512
ITS-Waukegan-Lewis Ave
IL Rte 173 to 14th St
Signals
Modernization
Upgrade traffic signal interconnect
Project Totals
B-01022
JULIE Locates 2013
@ Various
Maintenance
Preservation
JULIE Locates for Storm Sewers
Project Totals
$100,000
$100,000
$0
$100,000
$100,000
$0
$100,000
$0
$100,000
$100,000
$0
$1,210,000
$0
$1,210,000
$1,210,000
$0
$50,000
$0
$50,000
$50,000
$0
$174,100
$22,400
$174,100
$174,100
$22,400
$185,500
$5,300
$185,500
$185,500
$5,300
$100,000
$0
$100,000
$100,000
$0
U:\CPMS2000\cpmsdata\FY1318\CPMS Files\fy1318_6c.mdb - Ver. 6c, 6/13/2013 6:28:44 PM
Page 26 of 60
Mar-2015
$0
$100,000
CAD System Conversion
$100,000
$185,500
Project Totals
$0
$174,100
Install BlueToad Devices
$100,000
Program
Date
$0
$50,000
Project Totals
$100,000
$1,210,000
PASSAGE Field Support
$100,000
$100,000
Project Totals
$0
$100,000
PASSAGE Field Support
$100,000
$100,000
PASSAGE Field Support
Project Totals
B-01079
6-Year
County Revenue
$100,000
Project Totals
B-00970
6-Year
County Cost
Mar-2016
Mar-2017
Mar-2018
Jan-2014
Jan-2013
Nov-2010
Jan-2010
Mar-2013