Summary Transportation Improvement Program - Carryforward Amounts
Program Period: Fiscal Years 2013 to 2018 - Starting 12/1/2012
Selected: All
PIN
Route/From-To
Worktype/Cat
Project Description
6-Year
Total Cost
B-00474a
Fremont Center Rd Ext (1 of 2)
IL Rte 60 to Peterson Rd
Roadway
Expansion
New 2-Lane Road
$11,280,600
$11,280,600
$0
Mar-2015
B-00474b
Fremont Center Rd Ext (2 of 2)
IL Rte 60 to Peterson Rd
Roadway
Expansion
Developer Donation
$0
$0
$0
Aug-2013
$11,280,600
$11,280,600
$0
$13,700
$13,700
$0
$13,700
$13,700
$0
$768,000
$768,000
$0
$768,000
$768,000
$0
$0
$0
$0
$0
$0
$0
$6,279,000
$6,279,000
$0
$6,279,000
$6,279,000
$0
$4,177,100
$4,177,100
$1,793,600
$4,177,100
$4,177,100
$1,793,600
$54,000
$54,000
$0
$54,000
$54,000
$0
$100
$100
$0
$100
$100
$0
Project Totals
D-00377
Gages Lake Rd
@ US Rte 45
Intersection
Modernization
County Share of IDOT Project (C-91-208-00)
Project Totals
B-01170
Gelden Rd
Deep Lake Rd to Grass Lake Rd
Resurface
Preservation
2.25 HMA OVERLAY
Project Totals
B-00379
Gilmer Rd
@ Fish Lake Rd
Intersection
Modernization
Left turn Lanes/Traffic Signals
Project Totals
B-00728
Gilmer Rd
@ Midlothian Rd
Intersection
Expansion
Intersection Widening
Project Totals
B-00845
Gilmer Rd
@ IL Rte 120
Intersection
Modernization
Realignment
Project Totals
B-00920
Gilmer Rd
@Wildlife Way
Intersection
Modernization
Day labor project to add by-pass lane along Gilmer
Rd at Wildlife Way.
Project Totals
D-00603c
Golf Rd (3 of 3)
Sunset Ave to Greenwood Ave
Resurface
Preservation
Resurfacing
Project Totals
U:\CPMS2000\cpmsdata\FY1318\CPMS Files\fy1318_6c.mdb - Ver. 6c, 6/13/2013 6:28:44 PM
Page 18 of 60
6-Year
County Cost
6-Year
County Revenue
Program
Date
Jul-2010
Jan-2018
Jan-2019
Jan-2016
Jan-2019
Aug-2013
Dec-2012